PROJECT DOCUMENTATION
HIGHLIGHT
REPORT
Project:
Release:
Date:
PRINCE2
Author: |
Karthik Reddy Puram |
Owner: |
University of Bedfordshire |
Client: |
University
of Bedfordshire |
Document Ref: |
CATS/G4/CIS120-6 |
Version
No: |
1.1 |
1 Highlight
Report History
1.1 Document Location
This document is
only valid on the day it was printed. The source of
the document will be found at this location. 1.2 Revision History
Date of this revision: Date of next revision:
|
1.3 Approvals
This document
requires the following approvals.
Signed approval forms should be filed
appropriately in the project filing system.
Name |
Signature |
Title |
Date of Issue |
Version |
University of
Bedfordshire |
|
Project client |
23-10-2020 |
1.1 |
Ashish kumar
Reddy Ramidi |
|
Project
Manager |
23-10-2020 |
1.1 |
1.4 Distribution
This document
has been distributed to:
Name |
Title |
Date of Issue |
Version |
University of
Bedfordshire |
client |
23-10-2020 |
1.1 |
Ashish kumar
Reddy Ramidi |
Project
manager |
23-10-2020 |
1.1 |
Mehidia AfrinTania |
Team member |
23-10-2020 |
1.1 |
Rani Noothula |
Team member |
23-10-2020 |
1.1 |
Akash Dinkarkumar Patel |
Team member |
23-10-2020 |
1.1 |
Vijayakanth Dhulipalla |
Team member |
23-10-2020 |
1.1 |
Karthik Reddy Puram |
Team member |
23-10-2020 |
1.1 |
Sanjay Reddy perkit |
Team member |
23-10-2020 |
1.1 |
Amandeep Kaur |
Team member |
23-10-2020 |
1.1 |
2 Table of Contents
Page
1 Highlight Report History 1
1.1 Document Location 1
1.2 Revision History
1.3 Approvals
1.4 Distribution
2 Table of Contents
3 Date
4 Period
5 Status Summary
6 This Reporting Period
7 Next Reporting Period
8 Project and Stage Tolerance Status
9 Requests for Change
10 Key Issues and Risks
11 Lessons Report (if appropriate)
3 Date
This project
report has been started on 28-09-2020.
4 Period
The period of
the highlight report is covered from 19-10-2020 to 23-10-2020.
5 Status
Summary
The before 3
weeks of the project mainly working on the project management documentation. The
project mainly works on those three weeks the project brief, project initiation
document including risk response plan and the highlight report. And other two
documents like RACI matrix and Gantt chart those are included in the Project
Brief during this period.
The poster,
structure report, legal and ethical report, video, social media, lessons
learned report are additionally included in the next week For suppose week5.
Status of all
Project Tasks:
·
RACI matrix is Completed
Modified as per given Review from Client.
·
Gantt chart is completed.
·
Project Brief is completed
modified as per given Review from client.
·
Project Initiation document
also completed modified as per given review from client.
·
Highlight is completed and
submitted for Review.
·
Structure Report is in progress. Not yet
submitted.
·
The video is in the execution. Not yet
submitted.
·
Social media is in progress. Not yet
submitted.
·
Poster is waiting input from structured
Report. Not yet submitted.
·
Legal and ethical report id in progress. Not
yet submitted.
·
Lessons Learned report not yet started. Not
yet submitted.
6 This Reporting Period:
During this Reporting period, It basically focussed on passing on the endeavour the project documentation, for instance, project brief, project Initiation Document (PID) and the Highlight report. All these documentation has been made and submitted, but due to inconvenience of the project making, the gathering has not submitted the document before the deadline time and there has been a couple of changes done on the project brief, ProjectInitiation document (PID) and RACI Matrix during this period as per the suggestion from the client.
Work Package:
· In this report period, we have completed project brief and including Gantt chart Modified as per feedback from the client.
· In this report period, we have completed project Initiation document and including the Risk management plan also Modified as per feedback from client.
· We change the RACI matrix also as per the feedback from the client.
· Highlight report is completed and submitted for approval.
Initiation document (PID) and RACI Matrix
during this period as per the suggestion from the client.
7 Next Reporting Period
For this
Reporting period the project team needs to deliver undertakings which incorporates
the Structure report, legal and ethical report, video, Social media, Poster and
lessons learned report the last week has an individual intelligent report that
must be submitted.
Work
package:
·
Structure Report is in progress.
·
The video is in the execution.
·
Social media is in progress.
·
Poster is waiting input from structured Report.
·
Legal and ethical report id in progress.
·
Lessons Learned report not yet started.
8 Project and
Stage Tolerance Status
The Project needs to experience many
requirements, and tolerances to convey the task documentation effectively.
These tolerances are the limits set by the Project individuals, for viable
dynamic. The whole project team of 'DIGITAL MONEY' have set after tolerances:
Schedule Tolerance: First week, the group couldn't finish the given task inside the
schedule time period, as the undertaking was trickier.
Risk Tolerance: The project team investigated the Risk of correspondence holes
while creating project brief and further more project Initiation, and this
issue was settled by evading conflicting information flow.
9
Requests for Change
·
As per the request raised we
altered the duration video from1 minute to 5 minutes.
·
In project brief we sorted the
issue regarding team structure.
10
Key Issues and Risks
· Concerns related to digital money centre around their price volatility, ways of criminal behaviour, and environmental impacts.
· Changes have been done on RACI MATRIX about Roles and Responsibilities.
· Changes have been done on project Brief and Project Initiation document as per given by feedback from client.
11
Lessons Report (if appropriate)
The project team of DIGITAL MONEY, faced various inconveniences while building up the Project. A portion of the checks while building up the project are according to the given below:
- The team required a slight unwinding in the dispersed deadline time, as the team members didn't think about the bearing in the production of the task.
- Communication holes emerge at the same time, later on they were managed effectively